ITEM NO.2 COURT NO.11 SECTION IX
S U P R E M E C O U R T O F I N D I A
RECORD OF PROCEEDINGS
Petition(s) for Special Leave to Appeal (C) No(s).23949-23950/2017
(Arising out of impugned final judgment and order dated 04-08-2017
in WP No. 9315/2015 04-08-2017 in WP No. 4453/2014 passed by the
High Court Of Judicature At Bombay At Aurangabad)
AARNAVA PRECISION TECHNOLOGOIES LIMITED Petitioner(s)
VERSUS
POWER GRID CORPORATION OF INDIA LIMITED & ANR. Respondent(s)
(With Interim Relief)
Date : 18-04-2018 These petitions were called on for hearing today.
CORAM :
HON'BLE MR. JUSTICE ADARSH KUMAR GOEL
HON'BLE MR. JUSTICE ROHINTON FALI NARIMAN
For Petitioner(s) Mr. Shekhar Naphade,Sr.Adv.
Mr. Sanjay Kharde,Adv.
Mr. Shrikant Advant,Adv.
Mr. Samrat Shinde,Adv.
Mr. Sunil Kumar Verma, AOR
For Respondent(s) Mr. Maninder Singh,ASG
Mr. Pawan Upadhyay,Av.
Mr. Sumeet Joshi,Adv.
Mr. Sarvjit Pratap Singh,Adv.
Mr. Ratik Sharma,Adv.
For Ms. Sharmila Upadhyay, AOR
Mr. Kunal A. Cheema,Addl.Govt.Adv.
Mr. Nishant Ramakantrao Katneshwarkar, AOR
UPON hearing the counsel the Court made the following
O R D E R
Mr. Maninder Singh, learned Additional Solicitor General,
seeks time to take instructions as to how the safety may be insured
in the process of erecting the towers of the transmission lines and
if the work has already been executed and supply of electricity
commenced, what further steps are to be taken.
Signature Not Verified
Post after two weeks.
Digitally signed by
MAHABIR SINGH
Date: 2018.04.18
16:56:51 IST
Reason:
(MAHABIR SINGH) (SUMAN JAIN)
COURT MASTER BRANCH OFFICER
|